TRUSTED BUSINESS PARTNER

Experience

Al-Matek General Contracting Co.

Experience

Our Company has a specialized staff to construct big fiber optic network projects, mechanical, Electrical & civil works. Our staff pass's training in Generator , water & waste water ,fusion splicing & OTDR testing, construction supervision and construction reporting by foreign trainers which the certificate are attached for delegated manager & technical manager. 

Executed Works before Al Matek establishment are: 

1. Um Qasr Grain Silo: 

May 2003 to Oct.2003: Um Qasr port Grain Silo repair as subcontractor from Al Ebadi contracting company. The work included power and control design, installation and commissioning. All electrical and control drawings were in muss and ruptured, redraw and installation were our responsibility and the Silo returned back to service within four months. 

2. Um Qasr Dredge: 

Oct.2003 to Dec.2003: Saif Saad dredge maintenance and repair at Um Qasr port as subcontractor from Al Ebadi contracting company. The work included all mechanical, electrical and control. 

3. Water Projects: 

Dec.2003 to Oct.2004: Basra water plants refurbishment and maintenance under Bechtel Int. company contractor. The work was to clean and repair tanks, replace damaged electrical and mechanical parts replace or refurbish the exist center fugal pumps & submersible for the water treatment plants & the low lift plants ,also installing new compact unit ,installing the chlorination system and the construction work for most of Basra water treatment plants .

4. Sewage Projects: 

Sep.2004 to Janr.2005: Basra sewage plants refurbishment and maintenance under Bechtel Int. company contractor. The work was to clean and repair tanks, replace damaged electrical and mechanical parts & refurbish or install new center fugal pumps & submersible construct the steel structure of the screen & submersible guides and complete the civil works for most of the sewage plant in Basrah. 

5. CFN Project:

 Jan.2005 to Apr.2006: Consulted Fiber Network project under Bechtel Int. company contractor to connect southern and middle Euphrates power plants, 400Kv & 132Kv stations with Baghdad main control center by fiber optic cable. The work was to lay cables, splices and test. 

6. 5 Mile new market: 

May 2009: New 5 mile market in Basra governorate, the work was to supply and install electrical feeder cables and all power and lighting installations for 10 Nos. of shades (including earth system) containing 670 shopping space. 

7. Heavy equipment repairing 

Matek company has experience in supplying & refurbish generators in deferent sizes & to refurbish the heavy equipment like (crane ,fork lift , backhoe , shovel ….ets.) 

8. Buildings Refurbishment: 

In Oct.09 Al Matek Company involved as subcontractor in refurbishing schools and other buildings and got the desired appreciation regarding its doing. Al Matek Company also involved as subcontractor to refurbish Al Zubair ITPC building including telephone racks wiring. 

9. Steel construction.

Al Matek Company win contract with Basrah Governorate to Design & construct pedestrian bridge. 

10. Construction 

Win contract with Basrah Governorate to construct school 8 class in Al Dear . 

11. MV. Power Projects.  

 AL Matek Company successfully implemented Overhead Transmission Line & underground 11kv ( 3X 150 mm2 ) cables by Eni in Al Burjisyah .  Al Matek successfully implemented supply 18,000 meter of (1X300 mm2 ) cable & install two 33kv by Eni in Hammar Musrif between HOSS substation & New DGS ( Built by Samsung ) 

12. Delivering 

Our Company successfully implemented 32 Purchase Order with Shell Iraqi BV. In Majnoon , total Cost of the PO’s is (772,266.00 ) $ . also we successfully implemented two PO with Anton Company 

13. Our Company successfully implemented Fiber Optic Maintenance Project with Shell Iraqi BV.